Electrical work during a renovation: the order things happen in
When the electrician is needed during a renovation, and the decisions worth making before the walls close up.
Two visits: rough-in and fit-off
Electrical work on a renovation usually happens in two stages. The rough-in comes first, while walls and ceilings are open: cables are run to where every light, switch, power point and appliance will go. The fit-off comes at the end, after plastering, painting and cabinetry, when the fittings are installed, connected and tested. Knowing this helps you schedule the other trades around it.
Decide positions before the rough-in
Once the walls are lined, moving a power point or light means cutting into finished surfaces. Before the rough-in, settle the kitchen appliance positions, bench heights, bathroom layout, bedside and desk locations, and where you want switches as you walk into each room. A marked-up plan, or tape on the floor and walls, is enough for your electrician to work from.
Check the wiring and switchboard you already have
Renovations often expose old wiring and a switchboard that was never meant for a modern kitchen or extra air conditioning. It is worth having the existing installation checked at the start, so any upgrade can be planned into the job instead of becoming a surprise halfway through. New circuits also need safety switch protection, which an older board may not be able to take.